Project Information
Clients:
Josefin H. Smith
Category:
Building Construction
Complete Date:
25 January, 2023
Project Location:
258 Dancing Street, USA
Project Brief
A Modified Modular Construction Process
A modified modular construction process involves adapting traditional modular construction methods to meet specific project requirements, address unique challenges, or incorporate innovative approaches. Here's an outline of key components in a modified modular construction process:
Project Important Checklist
- The housekeepers we hired are professionals who take pride in doing excellent work and in exceed.
- The housekeepers we hired are professionals who take pride in doing excellent work and in exceed.
Constructed By

Ridsway Inc
10 McColgan Way Randoph, MA 02368
RIDSWAY INC
Work Report
- 8.8 million work hours
- 1,500+ employees on-site
- 51 cranes used during peak
Project Stats
- 7,400+ metric tons of steel
- 337 modules & Sections
- 1,000 linear meters
Post Views: 2